In agile, 6-8d is considered totally reasonable variance, while 2-12d simply isn't permitted. If that's the level of uncertainty -- i.e. people simply can't decide on points -- you break it up into a small investigation story for this sprint, then decide for the next sprint whether it's worth doing once you have a more accurate estimate. You would never just blindly decide to do it or not if you had no idea if it could be 2 or 12 days. That's a big benefit of the approach, to de-risk that kind of variance up front.