Importantly, though, only a small percentage of that capacity "in queue" will actually get built. From your link:
> Much of this proposed capacity will ultimately not be built, however, with only 23% of projects seeking connection from 2000 to 2016 having subsequently been built based on a LBNL analysis of a subset of queues. Only ISO-NE and ERCOT exceeded 30% completion rates, with CAISO performing the worst at 13%.