It was scheduled to take 54 months to build when construction started in 2007:
https://web.archive.org/web/20110613091002/http://www.neimag...
The last reactors to enter commercial operation in France, the 2 units at Civaux Nuclear Power Plant, took 13 and 11 years from construction start in 1988/1991 to commercial operation in 2002:
https://en.wikipedia.org/wiki/Civaux_Nuclear_Power_Plant
I wonder if EDF succumbed to hubris in thinking that they could build a new reactor design twice as fast as the last-completed reactors, or if they published optimistic numbers because they thought that there was more institutional tolerance for constant slippage than for estimating unhappily large numbers right at the start.